Info-Works

 

Rehabilitation Work on Rue Legault

Starting May 24, we will begin rehabilitation work on rue Legault, between Ste-Élisabeth and St-Paul (replacing the aqueduct and the sanitary sewer and adding a storm sewer). The work, which should last 9 weeks, will be done in 4 phases.

PHASE 1

Excavation work, replacement of the aqueduct and the sanitary sewer and addition of a storm sewer from rue Saint-Paul to rue Saint-Jacques 

Dates: May 24 to June 7
Impact: Street blocked in the work area, parking and mail delivery
Detour path Phase 1:

 

PHASE 2

Excavation work, replacement of the aqueduct and the sanitary sewer and addition of a storm sewer at the intersection of rue Legault and rue Saint-Jacques

Dates: June 7 to 14
Impact: Street blocked in the work area, parking and mail delivery
Detour path Phase 2:

 

PHASE 3

Excavation work, replacement of the aqueduct and the sanitary sewer and addition of a storm sewer from rue Saint-Jacques to rue Sainte-Élisabeth

Dates: June 14 to 28
Impact: Street blocked in the work area, parking and mail delivery
Detour path Phase 3:

  

PHASE 4

Paving, sidewalk, curbs and landscaping

Dates: June 28 to July 26
Impact: Punctual blocking of the street, parking and delivery of mail

Mitigation Measures:

  • Signalers will be present to facilitate traffic during Phase 4.
  • Temporary mailboxes have been installed and Canada Post supervisors will distribute the keys to residents shortly.
  • Temporary permits will be distributed by Municipal Patrol agents. Residents will be able to park their vehicles in adjacent streets, in the rue Christie parking lot, or in one of the two reserved spots in the Centre Harpell parking lot (for a maximum of 30 minutes).
  • Residents will be able to park their vehicles at their homes until the excavation is in front of their property.

Relevant details:

  • For the duration of the work, rue Legault will be in "local circulation only" mode between Sainte-Élisabeth and Saint-Paul streets.
  • The contractor will coordinate its work with Marché Richard deliveries
  • Starting May 22, making videos of the street and houses (outside and inside)
  • Starting May 21, installing temporary drinking water system
 

Rehabilitation Work on Chemin Sainte-Marie

In a first phase, will build a sidewalk at the southeast intersection of Des Pins and Chemin Sainte-Marie.

In a second phase, we will carry out major rehabilitation work (foundation and surface layer) on Chemin Sainte-Marie, between des Pins and the entrance to the Ecomuseum Zoo.

Phase I

Construction of a sidewalk at the corner of des Pins and chemin Sainte-Marie.

Dates: May 21 to 31
Impact: Alternative traffic on one lane
Mitigation measures: Two flagmen to facilitate traffic.

Phase II

Rehabilitation work on Chemin Sainte-Marie, between des Pins and the entrance to the zoo.

Dates: June 3 to 17
Impact: Complete closure of the work area
Mitigation measures: Detour path

 

REM Preparatory Work

In Sainte-Anne-de-Bellevue and the West Island, work will be carried out according to the following schedule*:

Planned schedule Work
Summer 2019 Construction of access roads
Fall 2019 to spring 2020 Construction of the elevated track superstructure (pile driving)
Spring 2020 Construction of reinforced earth walls
Spring 2020 to fall 2020 Construction of the elevated track superstructure (columns)
Fall 2020 Beginning of construction of the station
Spring 2021 to fall 2021 Construction of the elevated track superstructure (installation of segmented beams)
Summer 2022 Restoration and final landscaping work

*The current sequence is subject to change without notice.

The announcement of the transitional strategy for users of the Deux-Montagnes and Mascouche train lines was released on February 28th. 

Presentationhttps://rem.info/sites/default/files/document/Transitional-network-20190208-EN.pdf 

Datasheets for all sectors: EN : https://rem.info/sites/default/files/document/fiches-techniques-EN.pdf