Info-Work

 

Complete closure of des Pins road between Euclide-Lavigne and Poultry Cottages streets

The ministère des Transports will undertake night road works on des Pins road between Euclide-Lavigne and Poultry Cottages streets next June 17th, 18th and 19th.

Traffic will be detoured as pictured below. During this time, Euclide-Lavigne street will remain accessible for local traffic only.

This work will consist of:

  • Conduct corrosion surveys on Poultry Cottages viaduct.

Schedule of work:

  • June 17th 2019, from 10 pm to 5 am;
  • June 18th 2019, from 10 pm to 5 am;
  • June 19th 2019, from 10 pm to 5 am;

Possible nuisances:

Although everything is put in place to limit the impact of this work on local residents, some nuisances are possible, such as: closing of street, noise of construction machinery and recoil alarms, etc.

 

Work in the Sainte-Anne-de-Bellevue Train Station Parking Lot

Exo will carry out work in the parking lot of the train station on June 5, 10, 11 and 12.

From June 10 to 12, the portion of the parking lot located opposite the entrance to the station will be closed (29 parking spaces), and customers will be invited to use the available spaces in the gravel section (see photo below). During this time, bike racks will be moved to remain accessible.

This work will consist of:

  • Refurbish the sidewalk section where bike racks are located (1 week starting June 5)
  • Rearrange parking entrance
  • Redo the asphalt and the marking on the ground

Schedule of work:

  • 8 am to 3 pm

Nuisances possible:

Although everything is put in place to limit the impact of this work on customers and residents, some nuisances are apprehended, such as: closing of parking, noise of construction machinery and recoil alarms, etc.

 

Paving Work on Larry-Moquin Parking Lot

We will proceed with resurfacing work on the Larry-Moquin parking lot, located on Rue Sainte-Anne, at the corner of Montée Sainte-Marie.

The work is expected to last 2 weeks and to begin May 30th.

Impact:

Occasionnal traffic interference to give the machinery access to the construction site.

Mitifation measures:

Presence of a signalman to facilitate traffic.

 

Paving Work on Highway 40

The ministère des Transports will continue paving work on Autoroute 40 in the west island of Montréal, which began last fall. This year's work concerns the section between the Île-aux-Tourtes Bridge (excluding the bridge) and the boulevard des Anciens-Combattants.

Traffic Management - Significant Nighttime Closures in the Area

Starting May 27 until the end of July, partial and complete night closures will be required on Highway 40 (Félix-Leclerc) in either direction. The first interventions involve the roadway dedicated to eastbound traffic. During complete closures, road users will be redirected to the opposite road, in the opposite direction.

Île-aux-Tourtes Bridge

The interventions do not require any complete obstruction of Île-aux-Tourtes Bridge.. It should be noted, however, that bridge maintenance work is planned for this summer and for the next few months once this project is completed. As in previous years, dynamic traffic management will maintain three open lanes on the bridge in the direction of the peak. The schedule and details of the work will be communicated at the appropriate time.

In the event of adverse weather conditions or operational constraints, the work and detours could be postponed or canceled.

This project is listed in the 2019-2021 road investment list for the Montreal region. The Ministry thanks road users for their collaboration. In order to plan your travel appropriately, find out about current and future roadblocks by consulting Québec 511. For the safety of road users and workers, it is essential to respect signage in place.

 

Rehabilitation Work on Rue Legault

Starting May 24, we will begin rehabilitation work on rue Legault, between Ste-Élisabeth and St-Paul (replacing the aqueduct and the sanitary sewer and adding a storm sewer). The work, which should last 9 weeks, will be done in 4 phases.

PHASE 1

Excavation work, replacement of the aqueduct and the sanitary sewer and addition of a storm sewer from rue Saint-Paul to rue Saint-Jacques 

Dates: May 24 to June 7
Impact: Street blocked in the work area, parking and mail delivery
Detour path Phase 1:

 

PHASE 2

Excavation work, replacement of the aqueduct and the sanitary sewer and addition of a storm sewer at the intersection of rue Legault and rue Saint-Jacques

Dates: June 7 to 14
Impact: Street blocked in the work area, parking and mail delivery
Detour path Phase 2:

 

PHASE 3

Excavation work, replacement of the aqueduct and the sanitary sewer and addition of a storm sewer from rue Saint-Jacques to rue Sainte-Élisabeth

Dates: June 14 to 28
Impact: Street blocked in the work area, parking and mail delivery
Detour path Phase 3:

  

PHASE 4

Paving, sidewalk, curbs and landscaping

Dates: June 28 to July 26
Impact: Punctual blocking of the street, parking and delivery of mail

Mitigation Measures:

  • Signalers will be present to facilitate traffic during Phase 4.
  • Temporary mailboxes have been installed and Canada Post supervisors will distribute the keys to residents shortly.
  • Temporary permits will be distributed by Municipal Patrol agents. Residents will be able to park their vehicles in adjacent streets, in the rue Christie parking lot, or in one of the two reserved spots in the Centre Harpell parking lot (for a maximum of 30 minutes).
  • Residents will be able to park their vehicles at their homes until the excavation is in front of their property.

Relevant details:

  • For the duration of the work, rue Legault will be in "local circulation only" mode between Sainte-Élisabeth and Saint-Paul streets.
  • The contractor will coordinate its work with Marché Richard deliveries
  • Starting May 22, making videos of the street and houses (outside and inside)
  • Starting May 21, installing temporary drinking water system
 

Rehabilitation Work on Chemin Sainte-Marie

In a first phase, will build a sidewalk at the southeast intersection of Des Pins and Chemin Sainte-Marie.

In a second phase, we will carry out major rehabilitation work (foundation and surface layer) on Chemin Sainte-Marie, between des Pins and the entrance to the Ecomuseum Zoo.

Phase I

Construction of a sidewalk at the corner of des Pins and chemin Sainte-Marie.

Dates: May 21 to 31
Impact: Alternative traffic on one lane
Mitigation measures: Two flagmen to facilitate traffic.

Phase II

Rehabilitation work on Chemin Sainte-Marie, between des Pins and the entrance to the zoo.

Dates: June 3 to 17
Impact: Complete closure of the work area
Mitigation measures: Detour path

 

REM Preparatory Work

In Sainte-Anne-de-Bellevue and the West Island, work will be carried out according to the following schedule*:

Planned schedule Work
Summer 2019 Construction of access roads
Fall 2019 to spring 2020 Construction of the elevated track superstructure (pile driving)
Spring 2020 Construction of reinforced earth walls
Spring 2020 to fall 2020 Construction of the elevated track superstructure (columns)
Fall 2020 Beginning of construction of the station
Spring 2021 to fall 2021 Construction of the elevated track superstructure (installation of segmented beams)
Summer 2022 Restoration and final landscaping work

*The current sequence is subject to change without notice.

The announcement of the transitional strategy for users of the Deux-Montagnes and Mascouche train lines was released on February 28th. 

Presentationhttps://rem.info/sites/default/files/document/Transitional-network-20190208-EN.pdf 

Datasheets for all sectors: EN : https://rem.info/sites/default/files/document/fiches-techniques-EN.pdf