Info-Work

 

March 18th to April 24th - Chemin Ste-Marie

Closure of a lane on Chemin Ste-Marie between boulevard de L'Anse-à-l'Orme and 19,925 Ch. Ste-Marie (Cathelle). The other lane will alternate with construction site traffic lights, 24 hours a day for the duration of the work.

When: March 18th to April 24th
Where: Chemin Ste-Marie 



 

REM Preparatory Work

Date : Fall 2019 to Summer 2022
Where : North of Highway 40

Nature of work :
NouvLR, the consortium in charge of building the Réseau express métropolitain (REM), will procede to construction work in Saint-Anne-de-Bellevue from Fall 2019 to Summer 2022.

For more information on the construction of the REM in Sainte-Anne-de-Bellevue, visit https://rem.info/en/works-info/sainte-anne-de-bellevue

In Sainte-Anne-de-Bellevue and the West Island, work will be carried out according to the following schedule*:

Planned schedule Work
Fall 2019 to spring 2020 Construction of the elevated track superstructure (pile driving)
Spring 2020 Construction of reinforced earth walls
Spring 2020 to fall 2020 Construction of the elevated track superstructure (columns)
Fall 2020 Beginning of construction of the station
Spring 2021 to fall 2021 Construction of the elevated track superstructure (installation of segmented beams)
Summer 2022 Restoration and final landscaping work

*The current sequence is subject to change without notice.

The announcement of the transitional strategy for users of the Deux-Montagnes and Mascouche train lines was released on February 28th 2019. 

REM website : rem.info

Presentationhttps://rem.info/sites/default/files/document/Transitional-network-20190208-EN.pdf 

Datasheets for all sectorshttps://rem.info/sites/default/files/document/fiches-techniques-EN.pdf 

 

Environmental mitigation measures :

The REM project aims to integrate harmoniously with its immediate surroundings, which is why more than 85% of the work will be carried out on public domain, on existing road and railway rights-of-way. At the same time, however, some brush clearing and deforestation work will be realized in two sequences, before March 1st and after August 15th, which are necessary so the REM rail infrastructure, stations and access roads can be constructed. In the next few weeks, branch removal and tree and shrub cutting will take place in your sector.

Mitigation measures :

  • Work will be performed outside the nesting season (March 1st to August 15th)
  • These activities will be supervised and coordinated by our environmental experts, and will follow industry best practices and applicable standards and regulations;
  • At-risk plant species and trees will be relocated;
  • Through a reforestation program, the same number of trees that were cut in temporary construction zones will be replanted, and an additional 10% will be planted in the municipal territory or borough where the trees were cut.

The image below shows the sectors where site cleanup work is required :